Measurement and Verification (M&V) is a structured process that makes it possible to quantify, in an objective and reproducible way, the energy savings achieved by an energy efficiency intervention. In essence, it answers a precise question: has the implemented intervention produced the expected results?
The method is based on comparing the energy consumption recorded before the intervention - the so-called baseline - with that measured afterwards, taking into account all variables that may influence consumption: climatic conditions, operating hours, production levels, and changes in space usage.
The international methodological reference is the IPMVP - International Performance Measurement and Verification Protocol - developed by EVO (Efficiency Valuation Organization) and recognised in over 40 countries. In Italy, its use has become an operational requirement within several public incentive schemes.
Without independent verification of savings, any energy efficiency intervention remains an estimate. M&V transforms estimates into certified data, with concrete impacts on multiple levels:
In Italy, M&V is explicitly referenced in several regulatory and incentive frameworks.
The White Certificates scheme, managed by GSE and regulated by MiTE, recognises energy savings achieved through interventions on industrial plants, buildings, and networks. The quantification of savings—a necessary condition for issuing TEE - must follow standardised methods that largely overlap with IPMVP options. In particular, for measured projects (analytical sheets), IPMVP compliance is an explicit requirement.
The Transition 5.0 Plan - introduced by Law Decree 19/2024 and operational since 2024 - provides tax credits for investments in Industry 4.0 capital goods combined with a certified reduction in energy consumption.
The reduction must be documented through a sworn technical report certifying the actual savings achieved. IPMVP-compliant M&V is the most robust technical tool for producing this documentation in a defensible way.
The transposition of Directive 2012/27/EU introduced the obligation for large enterprises and energy-intensive companies to carry out energy audits. M&V integrates with this requirement: while the audit identifies savings opportunities, M&V verifies that subsequent interventions have actually delivered the expected savings.
The IPMVP protocol defines four methodological options, differentiated by level of accuracy, complexity, and cost. The choice depends on the type of intervention, the magnitude of expected savings, and the requirements of the applicable incentive scheme.
The four options, described in EVO documents and referenced in Italy by FIRE, are:
The following table summarises the main characteristics of each option to facilitate selection during the design phase of the M&V plan.

The M&V process is useful whenever it is necessary to demonstrate - not just estimate - energy savings. The main target groups are:
A well-structured M&V plan consists of distinct phases, which must be defined before implementing the measures - not afterwards.
Before any intervention, the objectives of the verification, system boundaries, parameters to be measured, and the most appropriate IPMVP option are defined. This phase is critical: decisions taken here determine the reliability and cost of the entire M&V activity.
Pre-intervention energy consumption data are collected, together with relevant adjustment variables (degree days, operating hours, production levels, etc.). The quality of the baseline is the factor that most influences the reliability of calculated savings.
The energy efficiency intervention is carried out. During this phase, monitoring and measurement systems foreseen in the plan are installed if necessary.
For a defined period (reporting period), actual consumption data and adjustment variables are collected. Duration and monitoring frequency depend on the selected IPMVP option.
Savings are calculated as the difference between the consumption that would have occurred without the intervention (adjusted baseline) and the consumption actually measured during the reporting period. Adjusting the baseline according to influencing variables is the core technical element of the calculation.
A certified PMVA (Performance Measurement and Verification Analyst) - a role recognised by EVO - verifies the accuracy of calculations, compliance with the M&V plan, and adherence to the IPMVP protocol. The independence of the verifier is a fundamental requirement for incentive schemes.
Results are presented in a structured M&V report, documenting methodology, data, calculations, and conclusions in a transparent and verifiable way. This document is the reference for accessing incentives and for contractual reporting.
Certimac’s Energy Area includes certified PMVA professionals qualified to carry out M&V activities in compliance with the IPMVP protocol. The approach is based on technical independence, calibrated instrumentation, and continuous updates on Italian and European regulations.
The support provided covers the entire lifecycle of an M&V project:
Certimac acts as a strategic partner for companies that want to turn their energy efficiency projects into concrete and measurable economic benefits, with an approach based on independence, expertise, and impartiality.
Discover all Certimac services for energy efficiency.
Contact our experts to understand how M&V can turn your interventions into certified savings and tangible incentives.
Fill in the form at the bottom of the page or write to energia@certimac.it.